Y-12 uranium facility hurt by contractor performance, other problems latest stockpile plan says

By ExchangeMonitor

Substandard contractor performance delayed the launch of a new Uranium Processing Facility at the National Nuclear Security Administration’s Y-12 National Security Complex in Tennessee until 2029, according to the agency’s latest annual progress report. 

The start of operations at the Uranium Processing Facility (UPF), a milestone known as CD-4, has now slid four years out to 2029. In 2022, the National Nuclear Security Administration (NNSA) acknowledged there would be a two-year delay. By the time the agency released its 2024 budget request, the delay had stretched to three or four years. 

Now, in the 2024 Stockpile Stewardship and Management Plan, the NNSA estimated UPF will begin operations in the last year of the decade owing to “contractor performance that was below expectations, direct and indirect impacts from the Coronavirus Disease 2019 pandemic, and labor availability and procurement costs,” NNSA wrote in the plan, an annual, unclassified progress report that this year runs more than 360 pages. 

“The project is undergoing a Federal re-baseline,” NNSA wrote in the report published, online and submitted to Congress on Nov. 27. Bechtel National is the lead contractor on UPF, doing the work as a subcontractor to Y-12 site prime Consolidated Nuclear Security, a team Bechtel leads.

UPF is designed to replace an older, existing facility that processes highly enriched uranium (HEU) for use in the secondary stages of nuclear weapons, in nuclear naval propulsion reactors and in other NNSA efforts. Topping the list of projects necessary for UPF to begin operation is shutting down the existing, 80-year-old Building 9212, where the most hazardous HEU work is done. 

The building does not meet modern safety standards, prompting the NNSa to move its functions to the new UPF. That likely will not be complete, paving the way for a CD-4 decision on UPF until the end of 2029, when the NNSA expects to “end dependency” on Building 9212, the report said.

“As part of the relocation strategy, modern capabilities will be deployed and existing processes will be simplified,’ the Stockpile Stewardship Plan said.

Comments are closed.

Partner Content
Social Feed

NEW: Via public records request, I’ve been able to confirm reporting today that a warrant has been issued for DOE deputy asst. secretary of spent fuel and waste disposition Sam Brinton for another luggage theft, this time at Las Vegas’s Harry Reid airport. (cc: @EMPublications)

DOE spent fuel lead Brinton accused of second luggage theft.



by @BenjaminSWeiss, confirming today's reports with warrant from Las Vegas Metro PD.

Waste has been Emplaced! 🚮

We have finally begun emplacing defense-related transuranic (TRU) waste in Panel 8 of #WIPP.

Read more about the waste emplacement here: https://wipp.energy.gov/wipp_news_20221123-2.asp

Load More