ICBM Fuse Program Faces Delays From Capacitor Issue

By Dan Leone

Complications with two nuclear-weapon refurbishment programs might delay production of new intercontinental ballistic missile fuses at the Kansas City National Security Campus by more than a year, Pentagon budget documents show.

The Air Force will need 10 months longer than expected, 41 months total, to purchase long-lead parts for the the ICBM Fuze Modernization program: a drive to replace the fuses that set of the W87 nuclear warheads of the Minuteman III and its planned successor, the Ground-Based Strategic Deterrent (GBSD).

That delay would have a cascading effect that pushes back Minuteman III test flights needed to sanity check the new fuse in real-life conditions, delaying mass manufacture of the final fuse design to some time in late fiscal 2025, instead of the middle of fiscal 2023 as planned a year ago. That is according to 2021 budget documents.

“The increase is due to delays in the Joint Navy (W88) and Air Force (B61-12) programs,” the Air Force said in its detailed 2021 budget justification.

Last year, the National Nuclear Security Administration (NNSA) announced it was scrapping plans to use commercial capacitors in the B61-12 gravity bomb and the W88 Alt-370 submarine-launched ballistic-missile warhead, delaying the first production of those refurbished weapons for the better part of two years: to 2022 and 2021, respectively.

Kansas City and the Sandia National Laboratories in New Mexico are now working on custom capacitors that can last as long as the refurbished weapons for which they are intended, but the effect on programs waiting to enter the production pipeline is now showing.

For the public, the most visible manifestation yet of this capacity crunch at the NNSA’s assembly hub for non-nuclear parts will be delays to future Minuteman III flight tests out of Vandenberg Air Force Base in California.

The service is halfway through a planned battery of four flight tests to evaluate the new fuses — the second launched Feb. 3 — and now will delay the third test flight to August 2022 from March 2022. The fourth flight will slip to February 2024 from November 2023, according to the Air Force.

Because full-scale production of 693 planned fuses cannot begin until after the test flights, the Air Force now expects Kansas City to start cranking out deployable fuses late in fiscal 2025, rather than in the middle of fiscal year 2023, according to budget documents.

The Air Force wants to start deploying GBSD in 2030 or so.

Comments are closed.

Partner Content
Social Feed

NEW: Via public records request, I’ve been able to confirm reporting today that a warrant has been issued for DOE deputy asst. secretary of spent fuel and waste disposition Sam Brinton for another luggage theft, this time at Las Vegas’s Harry Reid airport. (cc: @EMPublications)

DOE spent fuel lead Brinton accused of second luggage theft.



by @BenjaminSWeiss, confirming today's reports with warrant from Las Vegas Metro PD.

Waste has been Emplaced! 🚮

We have finally begun emplacing defense-related transuranic (TRU) waste in Panel 8 of #WIPP.

Read more about the waste emplacement here: https://wipp.energy.gov/wipp_news_20221123-2.asp

Load More