Meeting Set on Hanford PUREX Plant Tunnel Stabilization

A public meeting is planned for March 14 in Richland, Wash., on permit changes to support the Department of Energy’s plan to stabilize the second waste tunnel at the Hanford Site PUREX Plant. It also will cover actions already taken to stabilize the first tunnel at the plant.

After the older of two tunnels storing radioactive waste was discovered partially collapsed in May, a structural study was conducted of the second, longer tunnel. It found that the 1,700-foot-long tunnel built in 1964 also was a risk of collapse.

The first tunnel has already been filled with concrete-like grout for stabilization. In December, DOE said it also planned to fill the second tunnel with grout. It holds 28 railcars loaded mostly with large pieces of equipment that are contaminated with highly radioactive waste from the plant’s recovery of plutonium from irradiated fuel rods.

The decision will require a modification of the Hanford Site Dangerous Waste Permit issued by the Washington state Department of Ecology. Proposed modifications will cover information such as the grout formulation, the grout injection system, and alternatives available for eventual permanent closure of the tunnels. Grouting is considered an interim stabilization step.

The meeting will be held at 5:30 p.m. at the Richland Public Library, 955 Northgate Drive. Participation also will be available via webinar. The link and webinar ID can be found here.

In This Issue

More on This Topic


Environmental scientists in protective suits surveying contaminated soil at an industrial cleanup site.

Coming Up:

Here are events related to nuclear matters that Exchange Monitor staff are tracking:  OCTOBER: 27: Conference: The Energy Technology & Environmental Business Association (ETEBA) holds its annual business opportunities and technology conference at the Knoxville, Tenn., Convention Center.  28: Earnings call: Parsons will hold its quarterly earnings call with financial analysts starting at 8 a.m. […]