Weapons Complex Monitor Vol. 30 No. 15
Visit Archives | Return to Issue
PDF
Weapons Complex Monitor
Article 13 of 14
April 12, 2019

Energy Dept. Wants More Money for Santa Susana Work in Fiscal 2020

By Staff Reports

Funds for cleanup of the Energy Department’s footprint at the Santa Susana Field Laboratory (SSFL) in California would increase from $11 million in fiscal 2019 to $18 million in fiscal 2020, if Congress approves the Donald Trump administration’s budget request.

The department in this calendar year expects to issue the record of decision for environmental remediation of its 470-acre portion of the 2,850-acre SSFL. The document will lay out the environmental management approach in more detail than has been disclosed so far.

Boeing owns the sprawling property in Ventura County, Calif. The aerospace giant, along with DOE and NASA, are responsible for restoring the site.

The DOE Energy Technology Engineering Center (ETEC) at Santa Susana was used from the 1960s through the 1990s for research on nuclear power and liquid metal technology. The agency said in its fiscal 2020 budget justification it anticipates beginning decontamination and decommissioning of remaining structures at ETEC in 2020, based upon the as-yet-unpublished record of decision.

The Energy Department in 2017 signed a consent order on remediation with the California Department of Toxic Substance Control, the state regulator for Santa Susana. However, cleanup of soil and groundwater cannot start until both the federal record of decision and the state environmental impact report are issued, which is anticipated later this year.

Prior to 2007, the Energy Department did some dismantling and cleanup at ETEC under its Atomic Energy Act authority.

Eighteen DOE buildings still need to be decontaminated and torn down, according to the budget material. North Wind Group has a five-year, $26 million task order, which runs through September, to conduct environmental monitoring and surveillance, as well as demolition of the buildings.

Contractor CDM handles National Environmental Policy Act documentation for the project, such as the final environmental impact statement and the record of decision. Earlier this year it received a nine-month extension to its DOE contract, which would have otherwise expired on March 31. The DOE Office of Environmental Management said the extension should not raise the current task order value of about $32.4 million.

During fiscal 2020, the Energy Department is expected to publish the record of decision, commence decommissioning and tearing down remaining buildings, and submit its final groundwater corrective measures plan to California, among other work.

Comments are closed.

Partner Content
Social Feed

NEW: Via public records request, I’ve been able to confirm reporting today that a warrant has been issued for DOE deputy asst. secretary of spent fuel and waste disposition Sam Brinton for another luggage theft, this time at Las Vegas’s Harry Reid airport. (cc: @EMPublications)

DOE spent fuel lead Brinton accused of second luggage theft.



by @BenjaminSWeiss, confirming today's reports with warrant from Las Vegas Metro PD.

Waste has been Emplaced! 🚮

We have finally begun emplacing defense-related transuranic (TRU) waste in Panel 8 of #WIPP.

Read more about the waste emplacement here: https://wipp.energy.gov/wipp_news_20221123-2.asp

Load More