At Los Alamos

By Todd Jacobson

Mcmillan Lays out Needs for Pu Strategy

With a 2019 deadline to get out of the aged Chemistry and Metallurgy Research facility looming five years from now, Los Alamos National Laboratory Director Charlie McMillan this week outlined key requirements for the lab’s plutonium strategy. Testifying before the Senate Armed Services Strategic Forces Subcommittee, McMillan said the lab needed a steady funding stream and a smoothed-out project management process to ensure that it can modernize its plutonium capabilities and get out of CMR by 2019. After the deferral of the multi-billion-dollar Chemistry and Metallurgy Research Replacement-Nuclear Facility, the lab is pursuing a plan that would involve using existing facilities and building small modular facilities to maintain its plutonium work, but that plan remains in its infancy.

McMillan said the lab needs $90 million in Fiscal Year 2014, $38 million in FY 2015, and then a steady funding profile of about $85 million a year to 2019 for the plutonium strategy. "We need to get the money in that kind of sequence and we need to work very closely with NNSA so we don’t have the process getting in the way," McMillan told NS&D Monitor on the sidelines of the hearing. "If we can do those things I have high confidence we can meet a 2019 date. If we hiccup anywhere along that it’s now a very tightly wound system, and then I can’t say what I just said. We’re going to be in a position where success is not nearly as likely."

Pu Missions Could Be Jeopardized

McMillan’s written testimony was more dire in its analysis of the potential impact of not getting out of CMR by 2019. "Because of the delays in project start-up since the decision to defer CMRR-NF, I am concerned that we will miss the target date to terminate program operations in CMR by 2019," he said. "Should we be forced to terminate CMR operations before they can be transferred to CMRR-RLUOB and PF-4, our ability to execute plutonium missions will be jeopardized."

Phase one of the plan involves modifying the existing Radiological Laboratory Utility Office Building to increase the amount of radiological material allowed in the facility, and McMillan said in his prepared testimony that the lab was currently in the process of outfitting RLUOB with equipment that will allow it to take advantage of the increased material allowed in the building. Phase two involves reconfiguring the lab’s Plutonium Facility so that additional space can be devoted to analytical chemistry and materials characterization work, and phase three involves the construction of new "modular" facilities to handle either a plutonium storage vault, a pit processing facility, or a radiological diagnostics suite. "We will need space for these operations after we determine which is least appropriate for inclusion in our existing plutonium facility," McMillan said in his prepared testimony.

He added: "These modest steps should be sufficient to preserve our plutonium capabilities into the future and hopefully avoid some of the pitfalls we have experienced trying to construct very large multipurpose nuclear facilities over several decades. These additions are intended to ‘scale,’ not solve, most of the past acquisition challenges with ‘big box’ nuclear projects and be adaptable for a broad range of possible futures–not just at Los Alamos." He said the modular strategy would also extend the life of PF-4 for several decades. The alternative to the plutonium strategy, staying in CMR longer, is not pretty, he said. "That building will be 70 years old at that point. The nuclear facility standards were very different in 1952 when the building came on line," he said. "We do something like that, we have a gap in capabilities. But it’s probably early to really say what those consequences would be."

Comments are closed.

Partner Content
Social Feed

NEW: Via public records request, I’ve been able to confirm reporting today that a warrant has been issued for DOE deputy asst. secretary of spent fuel and waste disposition Sam Brinton for another luggage theft, this time at Las Vegas’s Harry Reid airport. (cc: @EMPublications)

DOE spent fuel lead Brinton accused of second luggage theft.



by @BenjaminSWeiss, confirming today's reports with warrant from Las Vegas Metro PD.

Waste has been Emplaced! 🚮

We have finally begun emplacing defense-related transuranic (TRU) waste in Panel 8 of #WIPP.

Read more about the waste emplacement here: https://wipp.energy.gov/wipp_news_20221123-2.asp

Load More